01Survey & engineeringLicensed surveyor establishes property line, MHWL, and existing-wall condition; structural engineer designs against hydrostatic head, soil surcharge, FEMA storm-surge cases, and 25-year design life. 14–28 days | 02PermittingFDEP Environmental Resource Permit, Sovereign Submerged Lands, Indian River County building permit, and community ARB submission filed in parallel where possible. 45–90 days | 03Mobilization & pile-driveSelf-mobilized barge, crane, and vibratory hammer; vinyl sheet piles driven to engineered refusal — typically 22 to 30 ft below the lagoon bottom. 5–10 days | 04Cap pour & tiebackFRP rebar cage, formwork, single continuous pour of 5,000-psi sulfate-resistant concrete; 316 stainless tiebacks to deadman anchors every fourth pile. Cap cures 7 days. 7–14 days | 05Backfill & finishClean #57 stone backfilled 3 ft behind the wall for drainage; final grade restored; turf reinstated; punch-list inspection with the homeowner and the county. 3–5 days |